There are four activities on the critical path. Coincidentally, their standard deviations are all equal to 4. The standard deviation of the critical path is therefore equal to: Multiple Choice 16. 64. 4. 2. 8.

Answers

Answer 1

Answer:

8

Step-by-step explanation:

Given that :

Number of activities = 4

Standard deviation of each activity = 4

Standard deviation of the critical path =?

To obtain the standard deviation of the critical path :

Take the square of each standard deviation:

Activity 1 = 4² = 16; activity 2 = 4² = 16 ; activity 3 = 4² = 16 ; activity 4 = 4² = 16

Sum of the squares :

16 + 16 + 16 + 16 = 64

Square root of the sum:

√64 = 8


Related Questions

can you solve this one to please?!

can you solve this one to please?!

Answers

Answer:

\(k = 1.9\) million

Step-by-step explanation:

\(34.6 - 15.5 = 19.1\)

\(2040-2004 = 36\)

In 36 years, the population will grow by 19.1 million.

\(\frac{36}{19.1} = 1.884 \approx 1.9\)

In 1 year the population will grow by 1.9 million.

3. Higher Order Thinking The
lengths of the pencils are
given at the right.
Write and solve a two-step
problem about the pencils.
6 cm
8 cm
10 cm

Answers

The lengths of the three pencils form a right-triangle, and the two-step problem is:

6^2 + 8^2 = 10^2100 = 100

How to write the two-step problem

The lengths of the pencils are given as:

6cm, 8cm and 10cm

Using the Pythagoras theorem, we have:

6^2 + 8^2 = 10^2

Evaluate the exponents

100 = 100

Hence, the lengths of the three pencils form a right-triangle

Read more about two-step problem at:

https://brainly.com/question/24590763

13. Justine is in the 6th floor when she got in t lift (elevator). The lift went 3 levels upward and levels downward. What level is she now? (1 mark) Answer:​

Answers

The level of Justine be after translation of lift remains same as initial condition,

⇒ level = 6.

Given that,

Justin is at 6th floor

Therefore,

In initial condition the level of Justine = 6

Now lift went 3 levels upward direction

Add the 3 to the initial level of Justine,

Then the level of Justine after such translation of lift = 6 + 3 = 9

Now lift went 3 levels downward

Now subtracting 3 form the level of Justine after moving upward,

Then the level of Justine after such translation downward = 9 - 3

                                                                                                  = 6

Then the final level of Justine after such translation of lift remains same as 6.

To learn more about word problem visit:

https://brainly.com/question/29203255

#SPJ1

We are given that y=-x+2. Let's substitute this
expression into the first equation and solve for x as
follows:
5 x-7 y =58
5 x-7 · (-x+2) =58
5 x+7 x-14 =58
12x =72
Finish the work above. What is x ? x=__

We are given that y=-x+2. Let's substitute thisexpression into the first equation and solve for x asfollows:5

Answers

The value of x in the equation is calculated as: x = 6.

How to Solve an Equation?

To solve the equation in order to find the value of x, we are to do the following as explained below.

By substitution, replace the y for -x + 2) into the equation, 5x - 7y = 58:

5x - 7(-x + 2) = 58

Apply the distributive property to open the parentheses:

5x + 7x - 14 = 58

Combine like terms

12x - 14 = 58

Add 14 to both sides:

12x - 14 + 14 = 58 + 14

12x = 72

Divide both sides by 12

12x/12 = 72/12

x = 6

The value of x = 6.

Learn more about solving equations on:

https://brainly.com/question/26310043

#SPJ1

The function f(x)=−3x+2 is defined over the domain −1

Answers

The domain of the function f(x) = -3x + 2 is (-∞, +∞), representing all real numbers, and the range is (-∞, 2], representing all real numbers less than or equal to 2.

The function f(x) = -3x + 2 is a linear function defined by a straight line. To determine the domain of this function, we need to identify the range of values for which the function is defined.

The domain of a linear function is typically all real numbers unless there are any restrictions. In this case, there is no explicit restriction mentioned, so we can assume that the function is defined for all real numbers.

Therefore, the domain of the function f(x) = -3x + 2 is (-∞, +∞), which represents all real numbers.

Now, let's analyze the range of the function. The range of a linear function can be determined by observing the slope of the line. In this case, the slope of the line is -3, which means that as x increases, the function values will decrease.

Since the slope is negative, the range of the function f(x) = -3x + 2 will be all real numbers less than or equal to the y-intercept, which is 2.

Therefore, the range of the function is (-∞, 2] since the function values cannot exceed 2.

For more such question on function. visit :

https://brainly.com/question/11624077

#SPJ8

In need of help immediately !!!

In need of help immediately !!!

Answers

Answer is 13 yards of ribbon

Step by step

She started out with $25
She had a remainder of $22.14

Subtract
25 - 22.14 = $2.86 she spent on ribbon

Divide $2.86 by .22 per yard = 13 yards

Problem solved

Which of the following numbers is rational?
A. 2.5
B. 25
C. 27
D. 257
Help my Dumba** should’ve went to class

Answers

Answer:

Step-by-step explanation:

C:27

Plzz give me brainliest

The answer is B) 25
Because it’s the only one that you can get a perfect square out of

Estimate the sum of the weights of Frailyn 10.2 pounds +611/12 pounds. Which statements are true about the estimate CHECK ALL THAT APPLY

 Estimate the sum of the weights of Frailyn 10.2 pounds +611/12 pounds. Which statements are true about

Answers

Answers:
6 11/12 should be rounded to 7
The estimated sun is 17 lbs
To find the estimated sun add 10+7

Object A is moving at 30 ft per sec. Object B is moving at 20 mph.​

Answers

Answer:

what we have to find or to prove.

A committee of four people is formed by selecting members from a list of 12 people.
How many different committees can be formed?

__ committees

Answers

The number of different committees that can be formed is 495

How many different committees can be formed?

From the question, we have the following parameters that can be used in our computation:

People = 12

Committee = 4

These can be represented as

n = 12 and r = 4

The number of different committees that can be formed is

Number = nCr

So, we have

Number = 12C4

Evaluate

Number = 495

Hence, the committee are 495

Read more about combination at

https://brainly.com/question/11732255

#SPJ1

What is the meaning of "A group G whose order is a prime number has only two subgroups, G itself and 1 = {1}"?

What is the meaning of "A group G whose order is a prime number has only two subgroups, G itself and

Answers

If G is not a cyclic group, then it does not have a subgroup of order p. Conversely, if G is cyclic, then it has a unique subgroup of order p.

The statement "A group G whose order is a prime number has only two subgroups, G itself and 1 = {1}" means that if G is a group with a prime number of elements, then the only subgroups of G are the trivial subgroup {1} and the group G itself.

In other words, there are no other proper subgroups of G besides these two.

The statement "A group G whose order is (p-1) where p is a prime number has a subgroup of order p if and only if G is cyclic" means that if G is a group with (p-1) elements, where p is a prime number, then G has a subgroup of order p if and only if G is a cyclic group.

In other words, if G is not a cyclic group, then it does not have a subgroup of order p. Conversely, if G is cyclic, then it has a unique subgroup of order p.

for such more question on prime number

https://brainly.com/question/18187355

#SPJ11

Diane bought new headphones originally listed for $70.99. They are 25% off. Which equation can be used to find the amount Diane will save?

Answers

Step-by-step explanation:

100% = $70.99

there is a discount of 25%.

that means 75% (100 - 25) of the original price remains.

the equation to get any x% amount of a 100% total is simply

x% amount = 100% total amount × x/100

25% = 70.99 × 25/100 = $17.75

A system has an MTBF of 2500 h. What is the probability that this system will survive 3000 hours without any failure if the failure is distributed exponentially?

Answers

It’s 15 to the hundredth power

Could you guys help me?

Could you guys help me?

Answers

Answer:

its 1881

Step-by-step explanation:

banakz akaknsz a a

It’s 1881 :) hope it helps

pls help!! please tell what the independent and dependent variables are, and a function that describes the situation. I will give brainly to whoever answers these!

pls help!! please tell what the independent and dependent variables are, and a function that describes

Answers

Step-by-step explanation:

Part A:

Given the entry fee of $35, the additional hourly rate of $5, and the total cost of $60:

The independent variable in this given problem is the number of hours, while the dependent variable is the total cost.  

An easier way to understand these concepts is to realize that the total cost depends on the number of hours you spend at the Snow Play Ski Park. The total cost changes by $5 for every hour you spend at the park.

The $35 entry fee is the constant, or the y-intercept. It is the initial cost that you have to pay given the 0 number of hours spent at the park.

Part B:

The function that represents the given situation is:

C(x) = 5x + 35

In order to determine how long can you be at the Snow Play Ski Park, substitute $60 as C(x) into the function:

C(x) = 5x + 35

60 = 5x + 35

Subtract 35 from both sides:

60 - 35 = 5x + 35 - 35

25 = 5x

Divide both sides by 5 to solve for x:

\(\frac{25}{5} = \frac{5x}{5}\)

x = 5

Therefore, if you have $60, then you can be at the Snow Play Ski Park for up to 5 hours.  

Note:

Please feel free to change the letter that represents the function to f ( x ) for Part B, if needed.

Jerome biked 1.2 miles. Then he ran 0.75 mile. How far did Jerome go you brainlyest if answerd by you

Answers

Answer:

The answer would be 1.95

Step-by-step explanation:

what is the following sum in simplest form? /8+3/2+/32

Answers

Answer:

C

Step-by-step explanation:

what is 0.5 as a fraction and 1.25 as a mixed number in simplest form

Answers

0.5= 1/2
1.25= 1 1/4

Answer:

Step-by-step explanation: 0.5 is 5/10 and 1.25 is 5/4

What is the range of the function shown on the graph above HELP

What is the range of the function shown on the graph above HELP

Answers

Answer:

C. 0 ≤ y ≤ 7

Step-by-step explanation:

Range is the interval of the numbers on the y-axis. The numbers go from y-value 1 to y-value 7. Since the circles at the ends are closed, this means 0 and 7 are included in the range, so ≤ is included instead of <.

Find the x- and y-intercepts for the following equation.
y = 2x + 4
x-intercept (x, y) = ()
y-intercept (x, y) = ()

Answers

Answer:

Step-by-step explanation:

y = 2x + 4

x-intercept y = 0

2x + 4 = 0

2x = -4

x = -2

(-2, 0)

y- intercept x = 0

2(0) + 4 = y

0 + 4 = 4

4 = 4

(0, 4)

Consider the function f ( x ) = cos ( 0.65 x ) f(x)=cos(0.65x). How much does x x have to vary for the argument of f f to vary by 2 π 2π?

Answers

We want to see how much must vary x so the argument of f(x) varies by 2 pi. We will see that x must vary (2π)/0.65.

So let's take the variation from 0 to 2π.

The argument is zero when x = 0

Argument = 0.65*x

if x = 0

Argument = 0.65*0 = 0

Now let's see which must be the value of x such that the argument is equal to 2π, so we must solve:

2π = 0.65*x

(2π)/0.65 = x

So we can see that x must vary from 0 to (2π)/0.65, or just a variation of (2π)/0.65.

If you want to learn more, you can read:

https://brainly.com/question/6904750

QUESTION 5: CALCULATIONS. a) b) c) 4.516 x 215 486,71 (29,774 +4,5) - 8 451 + 15​

Answers

a) 4.516 multiplied by 215 equals 971.54.

b) (29.774 + 4.5) minus 8,451 equals -8,416.726.

c) 486.71 minus (29.774 + 4.5) plus 8,451 plus 15 equals 8,903.451.

a) To calculate 4.516 multiplied by 215, we multiply the two numbers:

4.516 x 215 = 971.54

Therefore, the result is 971.54.

b) To evaluate the expression (29.774 + 4.5) - 8,451, we perform the addition and then the subtraction:

29.774 + 4.5 = 34.274

34.274 - 8,451 = -8,416.726

Therefore, the result is -8,416.726.

c) To calculate 486.71 minus (29.774 + 4.5) plus 8,451 plus 15, we first perform the addition within parentheses, then the subtraction, and finally the addition:

(29.774 + 4.5) = 34.274

486.71 - 34.274 = 452.436

452.436 + 8,451 = 8,903.436

8,903.436 + 15 = 8,903.451

Therefore, the result is 8,903.451.

For similar question on expression.

https://brainly.com/question/945593

#SPJ8

3. Which number is a natural number?
A-2.5
B 5-151
C-13+51
D|-81-2

Answers

Answer:

C

Step-by-step explanation:

A natural number is a number that you would use to count kids in a class for example. Like, 1,2,3,4 and so on. 2.5 is not a natural number since there cant be 2.5 of a student. 5-151 is a negative number and there cant be negative students. -13+51=38. 38 is a natural number. Now, in D it looks like there mightve been a absolute value sign but im not sure. If D has absolute value signs then D works too. Hope I could help.

if
\(16x - 3{x - 4}\)
please solve it for me​

Answers

Answer:

13x - 4

Step-by-step explanation:

16x - 3x - 4 = 13x - 4

13x-4
BECAUSE you can only subtract 16x & 3x because they both have variables. 16x-3x=13x
& since 4 doesn’t have a variable, it can’t do anything with 13x so it’s just at 13x-4

Look back at the plans these students used to solve the word problem below.

Who found a correct solution?

EK BAKI

The entire school, 250 students, went to the soap box derby.

The Math Club went in 2 vans, and each van held 6 students.

How many students from the Math Club went to the soap box

derby?

Paul added vans to students. Eva multiplied students by vans

Since 2+ 6 + 8, eight Math Club Since 6x2 = 12, twelve Math Club

students went to the soap box students went to the soap box

derby

derby

A. Eva

B. Paul

Answers

Answer:

A. Eva

Step-by-step explanation:

Given that

The entire school, 250 students, went to the soap box derby.2 vans went to soap box derby and each van held 6 students.

To find the total number of students from the Math Club who went to the soap box derby, we need to add the number of students in each van, the number of times equal to the number of vans.

i.e. by adding 6 (i.e. number of students in each van) 2 (number of vans )number of times, we can get the number of students from Math Club who went to the soap box derby.

Number of Math Club students who went to the soap box derby = 6 + 6 = 12

OR

Simply, multiply number of students in each van with the number of vans .

6 \(\times\) 2 = 12

Therefore, Eva is correct about the calculations.

pls check the attachment thank you​

pls check the attachment thank you

Answers

Answer:
351.86cm^3

Explanation:
Well, the volume of the part we need to take out is approximately 157.08cm^3 (with a radius of 2.5 and a height of 8). Now we have to find the volume of the larger cylinder (with a radius of 4.5 and a height of 8), which is approximately 508.94cm^3. Now subtract the volume of the little cylinder from the volume of the large cylinder (508.94cm^3 - 157.08cm^3). The volume of the metal casting is 351.86cm^3.
(your teacher might want you to round differently)
:)

Mamady is planning a trip. He will stay six nights at a hotel that charges $51.25 a night. What is a good estimate of the total amount he will pay for the hotel? 250, 300, 360, 50.

Answers

Answer:

Answer is 300

Step-by-step explanation:

because 51.25x6=307.5 and the closest estimate is 300.

Find the pressure in KN/m2 the exerted by a force of 90KN on an area 15m2

Find the pressure in KN/m2 the exerted by a force of 90KN on an area 15m2

Answers

The pressure for the force of 90 KN applied to the area of 15 square meters will be 6 KN/m².

What is pressure?

The force applied perpendicularly to an object's surface per unit area over which that force is distributed is known as pressure. In comparison to the surrounding pressure, gauge pressure is the pressure. Pressure is expressed using a variety of units.

Given that the force is 90 KN and the area of the application is 15 square meters.

The pressure is calculated by the formula:-

Pressure = Force / Area

Pressure = 90 / 15

Pressure = 6 KN / m²

To know more about pressure follow

https://brainly.com/question/13373498

#SPJ1

Product of (4a+6b)(a-b)

Answers

Answer:Simplifying

(4a + 6b)(a + -1b) = 0

Multiply (4a + 6b) * (a + -1b)

(4a * (a + -1b) + 6b * (a + -1b)) = 0

((a * 4a + -1b * 4a) + 6b * (a + -1b)) = 0

Reorder the terms:

((-4ab + 4a2) + 6b * (a + -1b)) = 0

((-4ab + 4a2) + 6b * (a + -1b)) = 0

(-4ab + 4a2 + (a * 6b + -1b * 6b)) = 0

(-4ab + 4a2 + (6ab + -6b2)) = 0

Reorder the terms:

(-4ab + 6ab + 4a2 + -6b2) = 0

Combine like terms: -4ab + 6ab = 2ab

(2ab + 4a2 + -6b2) = 0

Solving

2ab + 4a2 + -6b2 = 0

Solving for variable 'a'.

Factor out the Greatest Common Factor (GCF), '2'.

2(ab + 2a2 + -3b2) = 0

Factor a trinomial.

2((a + -1b)(2a + 3b)) = 0

Ignore the factor 2.

Subproblem 1

Set the factor '(a + -1b)' equal to zero and attempt to solve:

Simplifying

a + -1b = 0

Solving

a + -1b = 0

Move all terms containing a to the left, all other terms to the right.

Add 'b' to each side of the equation.

a + -1b + b = 0 + b

Combine like terms: -1b + b = 0

a + 0 = 0 + b

a = 0 + b

Remove the zero:

a = b

Simplifying

a = b

Subproblem 2

Set the factor '(2a + 3b)' equal to zero and attempt to solve:

Simplifying

2a + 3b = 0

Solving

2a + 3b = 0

Move all terms containing a to the left, all other terms to the right.

Add '-3b' to each side of the equation.

2a + 3b + -3b = 0 + -3b

Combine like terms: 3b + -3b = 0

2a + 0 = 0 + -3b

2a = 0 + -3b

Remove the zero:

2a = -3b

Divide each side by '2'.

a = -1.5b

Simplifying

a = -1.5b

Solution

a = {b, -1.5b}

Step-by-step explanation:

Solve the following inequality:

Solve the following inequality:

Answers

Answer:

\(r \geqslant - 16\)

Step-by-step explanation:

\( \frac{ - 10 + r}{2} \geqslant - 13\)

multiply both sides by 2:

\( - 10 + r \geqslant - 26\)

add 10 on both sides:

\(r \geqslant - 16\)

Answer:

\(r \ge -16\)

Step-by-step explanation:

To solve any equation/inequality:

1. get the variable to show up exactly once

2. isolate it

\(\frac{-10+r}{2} \ge -13\)

Multiply both sides by 2 and simplify (note that we're multiplying by a positive, not a negative, so the direction of the inequality stays the same, whereas multiplying or dividing by a negative would have changed the direction of the inequality)

\(\frac{-10+r}{2} *2 \ge -13 *2\)

\(-10+r \ge -26\)

Add 10 to both sides, and simplify

\((-10+r)+10 \ge (-26)+10\)

\(r \ge -16\)

Other Questions
is it true or false ? Anna has just read a text about New Zealand prime minister Jacinda Ardern and is conducting a research project based on the text.which research question would be most effective for her topic Write a discussion and analysis about. the half-wave rectifier ofg the operation help me again please. a solution has the 23.22% mass/volume of a particular solvent what is the mass of solute dissolved in 2.5 liter of solvent? question 20 options: 232.2 g 0.232 g 580.5 g 0.5805 g 5812.5 g what best explains the rapid rise in the popularity of rock music? Barbara's Bakery purchased furnishings (7 year property) 4 years ago. During the current year, she sold those assets. Her original cost in the furnishings was $15,000 and she did NOT use bonus depreciation in the year she purchased them. Due to other asset purchases that year, she has been using the mid-quarter convention when calculating the depreciation, and they were purchased in the second quarter of that year. If Barbara sold the furnishings in October of the current year (recovery period 4), how much depreciation will she will be able to deduct this year. (Use the MACRS tables at the end of the chapter to assist with this problem.)a. $898 b. $0 c. $1,796 d. $1,571 a user cannot access a server in the domain. after troubleshooting, you determine that the user cannot access the server by name but can access the server by ip address. what is the most likely problem? a lab group investigates the maximum weight students can lift with their arms compared to their legs. if their t' value was 0.35, which of the following conclusions would be justified? There is a new truck worth $31,500 and it loses value at the rate of 2.7% per year.1) Create an exponential model.2) How much is the truck worth 5 years later?3) How much is the truck worth 15 months later? 2 pages:Define the concept, example, attribute. What are the differenttypes of attributes ? Which types of attributes belong to class andpredictable quantity? Research the vulnerabilities called Heartbleed and Shellshock. Discuss how they affect a computer system. What will you do if a polyatomic ion is included in the ionic formula Which statement regarding the equation below is true?x+y-3 x+6 y=7 x+2A. It has a diameter of 18 units.B. It has an area of 36 square units.C. It has a center at (-5,3).D. It has a center at (-2,-3).ABCD what does this phrase mean "they have no natural predators." Could anyone give a hand? Define the key terms of neutrality in world war 1 Which sentence uses the word fanfare correctly?There was a lot of fanfare when the winners were announced.The children made great fanfare because there was only one treat left.The dog was brought to the fanfare to enjoy the afternoon.The clown demonstrated some fanfare for the audience. I need help with this. Lab: Conservation of Linear MomentumAssignment: Lab Report Urgent!! Find the magnitude of the net electric field at the origin (created by charges q1 and q2).