are liquidated damages intended only for missing the completion date of a project, or may they also be established for failure to meet mid-project interface dates?

Answers

Answer 1

Liquidated damages are established for both failure to fulfill mid-project interface dates and project completion dates, and are intended in both scenarios. They are recoverable for delays in the remaining work after substantial completion.

Amounts paid by the injured party as compensation for a specific contract formation breach are known as liquidated damages under contract law. These damages are compensated when a contract (or project) is not completed or when the completion deadline is not met.

Liquidated damages are typically tied to the project's "substantial completion date" (typically defined as the point at which the owner can use the project for its intended purpose); consequently, they are not typically enforceable.

To know more about liquidated damages click here:-

https://brainly.com/question/28498187

#SPJ4


Related Questions

What is true about single parent families? They face less stigma than nuclear families. They typically experience a higher income than nuclear families. They can have less conflict after a divorce than before one. All of the above

Answers

Answer:

They can have less conflict after a divorce than before one.

Explanation:

They can have less conflict after a divorce than before one" is the best option from the list since most of the conflict of divorce happens with couples, but this is not always true.

2
Which of the following is an example of an equity investment?
A. A loan.
B. A company bond
C. A government bond
D. A company's stock
Please select the best answer from the choices provided
OA
OB
OD
this and return
Save and Exit
Next
Subr

Answers

it's a loan and a government bond as well they offer funds to businesses

How did bank failures contribute to the depression ?

Answers

During the Great Depression, bank failures were a major contributor to the overall economic decline.

As banks failed and people lost their savings, it created a ripple effect that had a devastating impact on the economy. Banks that failed were unable to lend money to businesses, leading to a decrease in production and an increase in unemployment.

Furthermore, people had less money to spend, resulting in a decrease in demand for goods and services, leading to further economic contraction. Bank failures were a major factor in the economic downturn of the 1930s, and their effects were felt throughout the nation.

To learn more about bank, click here:

https://brainly.com/question/14042269

#SPJ4

What kind of psychologist would someone who is dealing with the loss of a loved one most likely visit?

Answers

Answer:

Counseling psychologist

Explanation:

I just took the test! Good luck :)

the board of directors of herbalife nutrition approved a 5-for-2 stock split. after the split, how many shares of herbalife stock will an investor have if he owned 520 shares before the split?

Answers

After the 5-for-2 stock split, the investor would have 1300 shares of Herbalife stock.

A stock split is when a company decides to increase the number of its outstanding shares by issuing more to current shareholders. In this case, the split ratio is 5-for-2, which means for every 2 shares an investor owns, they will receive 5 new shares. So if the investor owned 520 shares before the split, they would receive 1300 new shares (520/2 = 260 x 5 = 1300). The total number of shares the investor will have after the split is 1820 (520 + 1300). A stock split does not change the value of the investment, it only changes the number of shares an investor holds. However, it can make the shares more affordable to other investors and potentially increase liquidity.

To know more about stock visit:

https://brainly.com/question/31940696

#SPJ11

Kaylee's refrigerator suddenly breaks down. It's old and would be expensive to repair, so she decides to buy a new one. Kaylee chooses a refrigerator with a 12-month, no-interest financing offer. The sales agreement lists the sale price, the amounts and dates of payments, the APR that will apply if Kaylee doesn't pay off the refrigerator in 12 months, and a lot of other information. The law that requires sellers to provide this information to purchasers is

Answers

Kaylee's refrigerator suddenly breaks down. It's old and would be expensive to repair, so she decides to buy a new one.  The law that requires sellers to provide this information to purchasers is "The Truth-in-Lending Act". This is further explained below.

What is The Truth-in-Lending Act?

Generally,  In 1968, Congress passed and President Nixon signed the Truth in Lending Act (TILA) to protect customers from dishonest lenders.

In conclusion, Kaylee's fridge has broken down unexpectedly. Being too old and costly to fix, she opts to replace it instead. The "Truth-in-Lending Act" is the piece of legislation that mandates vendors provide this data to buyers.

Read more about The Truth-in-Lending Act

https://brainly.com/question/7696024?referrer=searchResults

#SPJ1

Knopp Company experienced an event that had the following effects on its financial statements.

Answers

The occurrence that Knopp Company dealt with had the following effects on its financial statements: Earned cash revenue.

Effects:

Earning cash revenue indicates that the organisation has made cash sales.Cash is received and income is received in the case of cash sales.As a result, assets (cash) grew. Additionally, as income rises, equity rises as well.Both revenue and net profit rise as a result.Cash flow from operating operations also refers to this.

The above transaction has the following outcome:

               Balance sheet Income Statement                Statement of

Assets  =  Liabilities  +  Equity   Rev.  −  Exp.  =  Net Inc. Cash Flows

+      NA   +       +    NA         +             + OA

To know more about Financial Statements, refer to this link:

https://brainly.com/question/14951563

#SPJ4

Why is it called Chick-Fil-A when a Fil-A (filet) is normally cooked with beef???

Answers

Because most of their food consists of chicken? They barely have any beef on their menu
It is a cleaver marketing strategy. One of Chick-Fil-A’s missions is to encourage people to eat chicken instead of meat, so a funny twist they thought they should include is a name spin. Like you have stated, a Filet is normally a steak, but Chick-Fil-A spiced it up a little bit and changed the context behind it to fit their brand of boneless chicken :)

Max is using a search engine to do research on trends in his industry when he comes across a website that isn’t necessarily related to his research–but is interesting and engaging. Without realizing it, Max spends over an hour browsing through the webpage’s numerous articles and links. When his boss asks him if his research report will be ready by the end of the day, Max isn’t sure how to respond. He’s hardly done any work–but it’s not like he was purposely avoiding work. He was using the search engine for the purpose of research, after all. It’s not his fault that the search results weren’t very relevant. Max is considering asking his boss for an extension on his deadline so that he can spend more time researching. What do you think? What should Max do?

Answers

In this situation, Max has to first give his boss some advance notice that he wont be able to complete the report before deadline, explain himself briefly as to why that is, then ask for more time to be able to complete the task.

What is a deadline?

A deadline indicates that a task or project is anticipated to be finished by that date and time. There is a clear expectation of what must be provided and by when thanks to deadlines. Employees are able to take charge of their work in this way and include deadlines into their time management techniques.

It's critical to schedule deadlines in advance because your work may be delayed. Recognize that some resources might be delayed and that some people might not be available. You may prevent the disaster of missing a deadline by making plans in advance.

Deadlines are crucial in business for a variety of reasons. They establish standards and encourage productive behavior in the workplace.

Learn more about deadlines here https://brainly.com/question/14312055

#SPJ1

What is another term for property insurance

Answers

Answer:

Hope it helps you. :)))

Explanation:

Property insurance provides protection against most risks to property, such as fire, theft and some weather damage. This includes specialized forms of insurance such as fire insurance, flood insurance, earthquake insurance, home insurance, or boiler insurance.

What are the factors of production?
a. Goods and services
b. Risk and opportunity
C. Land, labor, & capital
d. Wages, salaries, & profits

Answers

Answer:

C.Land,labor & capital

is the term used to describe a substantial gift of money or property from the groom and his kin to the bride and her kin.

Answers

Bride price is the term used to describe a substantial gift of money or property from the groom and his kin to the bride and her kin.

What do you mean by the Bride price?

Bride Price can be defined as the concept in which  the family of the groom pay their future in-laws at the start of their marriage. It can be in the form of  money, presents, or a mixture of both. It is currently practised in Thailand, China, and Papua.

The main purpose of bride price includes paying for the future labour inputs of their daughter and her unborn children. It also symbolises  that a man has kept his treasure  where his heart belongs, that is the bride.

There are certain disadvantages related to bride Price including making marriage unequal. The woman tends to become an article of property in her home. It leads to 'commodifying' human relationships.

To know more about Bride price from the given link.

https://brainly.com/question/20515983

#SPJ4

a market includes group of answer choices buyers only. sellers only. both buyers and sellers. the place where transactions occur but not the people involved.

Answers

A market includes both buyers and sellers. A market is a social arrangement where buyers and sellers come together to engage in the exchange of goods, services, or resources.

It is characterized by the interaction between these two parties, with each having a specific role to play. Buyers are individuals or entities who demand a product or service, while sellers are those who supply the desired goods or services.

The essence of a market lies in the interaction and exchange between buyers and sellers. Both parties participate in the market to fulfill their respective needs and objectives. Buyers seek products or services that satisfy their wants or requirements, while sellers offer their goods or services to meet those demands. This dynamic interaction between buyers and sellers forms the foundation of a market.

While a market can refer to the physical place where transactions occur, such as a marketplace or an online platform, it extends beyond the physical location. It encompasses the entire system and process of buying and selling, including the individuals involved, their actions, and the exchange of value that takes place.

Learn more about dynamic here:

https://brainly.com/question/29451368

#SPJ11

Ava studied marine biology in college. What company might be interested in hiring Ava?

A.
a seafood restaurant looking for a sous chef

B.
an island hotel in need of a manager

C.
a large aquarium looking for a technician

D.
an airline looking for a flight attendant

Answers

Explanation:

Aquarium Technician Job Offer.

Nehal Kafle

Ava studied marine biology in college. What company might be interested in hiring Ava?

A large aquarium looking for a technician might be interested in hiring Ava since she studied marine biology, which is related to the aquatic environment and marine life. As a technician in an aquarium, Ava could be responsible for monitoring and maintaining the aquarium's marine animals, their habitats, and the water quality. She could also assist in research and education programs related to marine life. Therefore, option C would be the most suitable company for Ava based on her field of study.

Answer:

Explanation:

Actually it is C a large aquarium looking for a technichian

Starling is evaluating Bond prices and have requested your help. Below information
is provided.
C = Coupon = 10%, interest rate = ytm = r = 12%, Maturity = N or T = 10 years, P =
price, Par = $1,000
What is the bond’s price using semi-annual compounding?

Answers

To calculate the bond's price using semi-annual compounding, P = (C / 2) * (1 - (1 + r / 2)^(-2N)) / (r / 2) + Par / (1 + r / 2)^(2N), needs to be solved.

The price of a bond can be determined by discounting the present value of its future cash flows, which include the periodic coupon payments and the principal repayment at maturity. In this case, the bond has a coupon rate (C) of 10%, an interest rate or yield to maturity (ytm or r) of 12%, a maturity period (N or T) of 10 years, and a par value (Par) of $1,000.

Since the bond has semi-annual compounding, we need to adjust the coupon rate and yield to maturity accordingly. The semi-annual coupon rate is calculated by dividing the annual coupon rate by 2 (10% / 2 = 5%), and the semi-annual yield to maturity is calculated by dividing the annual yield to maturity by 2 (12% / 2 = 6%).

Next, we can use the present value formula to calculate the bond's price. The formula is:

P = (C / 2) * (1 - (1 + r / 2)^(-2N)) / (r / 2) + Par / (1 + r / 2)^(2N)

By plugging in the values into the formula and solving for P, we can find the bond's price using semi-annual compounding.

Learn more about semi-annual compounding here:

https://brainly.com/question/29766128

#SPJ11

When a company has a diverse workforce, which of the following is likely to
be true?
A. Wages can be decreased.
B. There is potential for discrimination.
C. The workforce will be all male.
D. HR managers will be all males.

Answers

i think it’s D but i’m not sure

The correct option is D. When a company has a diverse workforce, HR managers will be all males is likely to be true.

Because every team member—from the leadership to the frontline staff to mobile workers—brings their own distinct backgrounds, experiences, and viewpoints to the table, workplace diversity fosters creativity and innovation.

How does diversity affect the workplace?

Productivity is strongly impacted by the greater variety of talents and abilities that come with workplace diversity. Because diverse employees have a range of talents, skills, and preferred fields of work, workplaces with greater variety typically have higher productivity.

Beyond political correctness, a diverse workforce has several advantages. Including people from all backgrounds and viewpoints can promote better decision-making, more innovation, and increased workplace engagement. Additionally, it might enhance a business's reputation and make it simpler to draw in top employees.

Thus, The right answer is D. A corporation is more likely to have all male HR managers if its workforce is diverse.

Learn more about A Diverse Workforce here:

https://brainly.com/question/18956431

#SPJ6

How is Ramadan celebrated?

Answers

Answer:

As a Muslim, you can celebrate Ramadan with family or/and with friends and other families. In Ramadan if you are young you get a certain amount of money form your elders and the most important thing is eat! After one month of not eating you should have fun and eat really good foods. I hope this helped!! :)

Answer:

During Ramadan Muslims abstain from food and drink during daylight hours. This fast, called sawm, is one of the five pillars of Islam. To get through a long day without food, Muslims will often wake up early to eat a meal called suhur before daybreak.

Explanation:

Your manufacturing requires parts to go sequentially through process A, B, and C. A machine can do process A in 1
minute, B in 2 minutes, and C in 3 minutes. You have two A machines, one B machine, and tree C machines. Which process is the bottleneck
(can produce the fewest items per unit time)?

Answers

Answer:

Process B

Explanation:

Got it right

What grade are y’all in ? So I can give some advice ! Middle school or high school ?

Answers

Answer:

Im in middle school, 7th grade

Explanation:

Some advice would be great :)

3. ______ are defined as goods or services that are required for health and safety.

Answers

Occupational Health and Safety are defined as goods or services that are required for health and safety. Information standards are guidelines governing the information that must be provided to consumers when they purchase specific goods.

What is the safety of goods?

A safe product is one that delivers either no risk or a minimum tolerable level of risk, taking into account the product's typical or reasonably foreseeable use and the need to maintain a high level of consumer protection.

Occupational health and safety is a multidisciplinary discipline that deals with all elements of workplace health and safety, with a heavy emphasis on preventing workplace dangers.

Learn more about the safety of goods here:

https://brainly.com/question/28480753

#SPJ1

You are choosing the color scheme for a Web page. Which color is considered the color of extremes and is used to capture attention, and to indicate danger and anger? A: Green B:Red C: yellow D: purple thank you<3

Answers

Answer:

Red

Explanation:u

Red is the color of extremes. It's the color of passionate love, seduction, violence, danger, anger, and adventure.

The red color is associated with the extremes and is used to attract attention, as well as to symbolize danger and wrath, and this is the color scheme of the web page.

What is a web page?

A web page is a simple document that a browser may display.

HTML is the language used to create such documents (which we look into in more detail in other articles).

A web page can contain a number of resources, such as style information, which controls the look and feel of the page.

The red color represents the extremes. This color is connected with passionate love, seduction, aggression, danger, rage, and adventure.

Therefore, option B is correct.

Learn more about the web page, refer to:

https://brainly.com/question/9060926

what is the most compelling reason to regularly evaluate progress against the project plan?

Answers

The most compelling reason to regularly evaluate progress against the project plan is to ensure that the project is on track and to identify any potential issues or roadblocks early on.

By monitoring progress and comparing it to the plan, project managers can make informed decisions and take corrective action if necessary. This can help to prevent delays, cost overruns, and other project failures.

Regular evaluation also allows for better communication with stakeholders, as project managers can provide updates on progress and any adjustments made to the plan. This helps to build trust and confidence in the project team and the overall project.

Additionally, evaluating progress against the project plan can help to identify areas for improvement and best practices that can be applied to future projects. By analyzing what worked well and what didn't, project managers can learn from their experiences and continually improve their project management skills.

Overall, regular evaluation of progress against the project plan is crucial for successful project management. It ensures that projects stay on track, stakeholders are informed, and valuable lessons are learned for future projects.

To know more about plan  visit

https://brainly.com/question/31172525

#SPJ11

Statement 1: In horizontal analysis of the balance sheet, total assets are represented by 100%.
Statement 2: Common-size statements are statements of companies of similar size and operations.
A. Both statements are true
B. Both statements are false
C. Only statement 1 is true
D. Only statement 2 is true
Please provide a comprehensive explanation for your answer.

Answers

The correct answer is:   B. Both statements are false.

1. Statement 1: In horizontal analysis of the balance sheet, total assets are represented by 100%.

This statement is false. In horizontal analysis, also known as trend analysis, the items in the financial statements are compared over a period of time to identify changes and trends. It involves calculating the percentage change in each line item relative to a base year or period. The base year or period is usually represented as 100%, and the subsequent periods are expressed as a percentage of that base.

However, in horizontal analysis of the balance sheet, it is typically the individual line items that are represented by 100% in the base year or period, not the total assets. Each line item is expressed as a percentage of its value in the base year or period to analyze the changes and trends in the specific components of the balance sheet.

2. Statement 2: Common-size statements are statements of companies of similar size and operations.

This statement is false. Common-size statements, also known as vertical analysis, are financial statements in which each line item is expressed as a percentage of a base amount within the same statement. The base amount is usually the total for that particular statement.

Common-size statements are not specific to companies of similar size and operations. They are used to compare the relative composition of financial statements within the same company over time or to compare the financial statements of different companies in the same industry. By expressing each line item as a percentage of the total, it allows for a better understanding of the relative importance of each component within the financial statement.

Therefore, the correct answer is B. Both statements are false.

Learn more about horizontal analysis here:

https://brainly.com/question/29392869

#SPJ11

international business machines (ibm) has earnings per share of $6.85 and a p/e ratio of 15.19. what is the stock price?

Answers

International Business Machines (IBM) has a stock price of $104.05. Its profits per share are $6.85, and its price/earnings ratio is 15.19.

What sort of deal did you just make when you bought a share of IBM stock on the New York Exchange?

You took part in a transaction on the futures market if you just bought a share of IBM through a New York Stock Exchange-based transaction.

Which of the following can help managers act in a way that supports shareholders' objectives?

A board of directors that is independent, with well-designed management compensation.

What exactly is IBM's employee stock purchase plan?

The plan offers a variety of customizable services to help you manage your investment and is intended to give people an easy and convenient way to buy, hold, and sell IBM common shares.

To Know more about earnings ratio

https://brainly.com/question/15520260

#SPJ1

Which one is not a Function in MS Excel?

MAX
ARG
MIN
SUM

Answers

ARG is not a function I’m familiar with in Excel, however I’m familiar with MAX, MIN, and SUM in Excel.

There for the answer is ARG.

Which is a steppingstone towards future education

A. A high school diploma
B. On the job training
C. Vocational courses
D. Technical courses

Answers

Answer:

a high school diploma or on the job training

Define the word investing!

Thanks!

Answers

Answer:

To put money into Bank business property share accept in hope that you will make a profit. To spend money,time or energy on something that you think is good or useful.

Explanation:

If you like my answer than please mark me brainliest thanks

What are three elements of negligence?
Actual Harm
Breach of duty
State of mind
Duty of care
Proximate cause
Motive

Answers

Answer:

actual harm

breach of duty

duty to act

What is a common consequence for an athlete who is been found to have used a banned drug a major competition

Answers

Answer:

Athletes who are found to have used such banned substances, whether through a positive drugs test, the biological passport system, an investigation or public admission, may receive a competition ban for a length of time which reflects the severity of the infraction.

Explanation:

Answer:

down below

Explanation:

A common form of punishment is disqualification from the sport they are competing in, a temporary ban from the sport, revoking their prize, and, in a few cases, permanent ban from competing in the sport they were found with the drug.

You can look up news articles to get more information.

Hope this helps! :)

The main source of finance for public corporations is s _ _ _ _ f _ _ _ _ _ _ (from t _ _) ​

Answers

Answer:

tax

Explanation:

the tax is a national practise carried all over the country